4.7 Commissioning
General commissioning process
1) Remove all residual installation and connection materials from the connection area.
2) Before commissioning, check all screw and terminal connections for tightness.
3) Check whether all unused cable screw connections are properly sealed with blind plugs or dummy screw
fittings.
4) Ensure that the voltage of the power supply line is switched on. The status LED (LED bar) should start to
slowly flash green after 15-20 seconds.
The device performs a self test every time it is switched on.
5) Perform the specified initial tests according to the locally applicable regulations and laws (see Chapter "
4.7.1 Commissioning mode/self test [34]").
6) Close the connector panel cover to the charging station.
7) Mount the housing cover (see Chapter " 4.7.5 Mounting the housing cover [37]").
4.7.1 Commissioning mode/self test
The charging station can be placed into a commissioning mode for supporting the initial system test. During
this, a self test of the device is performed (interlocking, contactor activation, current measurement, etc.) and
the result is displayed.
After successful test without connected vehicle, the contactor is switched for limited time in order to facilitate
the initial tests. A normal charging procedure is not possible in commissioning mode. The interlocking of the
connector socket is activated to prevent a cable from being plugged in.
A switching on of the charging station in commissioning mode via the power supply line leads to a fault for
safety reasons (white-red-red-red) in order to prevent an unintended activation.
Activating the commissioning mode
Set the DIP switch DSW2.8 to ON (see " 4.6 DIP switch settings [31]").
Perform a reset of the charging station. To do this, press the [service button] for 1second.
The commissioning mode is now activated and signalized by the orange status LED.
You now have the option for approximately 5 min. to contact with standard test probes using the measur-
ing device ( e.g. Astaco® test probes from BEHA) and to perform the necessary tests (see Chapter "
4.7.2 Safety checks [35]").
After 5 min. have elapsed, the contactor is deactivated in the charging station is shut down.
Deactivating commissioning mode
Set the DIP switch DSW2.8 to OFF again.
Perform a reset of the charging station. To do this, press the [service button] for 1second or switch the
power supply off/on.
The charging station starts up again in normal mode and is ready for operation.