10.5 Access Protection
To guarantee 24-hour continuous operation you should place the KCS system at a place where
unauthorized access is impossible. The power supply has to be protected from unintentional disconnection.
10.6 Dust Protection
The room where the KCS system is placed should be free of dust and other air pollution (like normal office
environment).
10.7 General
It is recommended to use a separate power circuit or an uninterruptible power supply (UPS). Depending on
the installation the customer must provide two or more power sockets.
10.8 Cabling
Public Services
In case the connections of your public services (fax, telex ...) are to be moved to another place or have to
be installed new this work has to be done by your local PTT authorized partners. Take into consideration
that PTT works could take some time.
Note: The connections must be provided in operating condition at the agreed installation date.
Asynchronous Connections
Only shielded cables should be used to ensure proper operation to avoid any electric or magnetic
interference.
For the maximum cable length individual EDP specifications are valid. If modems (or in-house modems) are
required it is up to the customer or its subcontractor to have them installed and working. The proper
operation of the connection must be checked by connecting a terminal.
Note: The connections must be provided in operating condition at the agreed installation date.
Cable Form
The cable has to be in one piece from end to end. It is not allowed to put more pieces together. Cables to
ISDN, Analogue or E&M devices must be shielded and have to be equipped with ferrite cores provided by
Kofax. The cores must be mounted as near as possible to the KCS Server. The cable has to be wound
around the core twice (turns as far apart as possible). Cabling has to be 26 AWG (0,13mm²) size as a
minimum.
Cabling Work
The cabling work cannot be performed by your KCS engineer. Please have this work done by your
company electrician. On each end there have to be some meters left for later movements, plug mounting
and maintenance.