3 INSTALLATION
34
OPTIWAVE 5200 C/F
www.krohne.com 07/2013 - 4001904902 - HB OPTIWAVE 5200 R02 en
Bypass chambers
Installation next to tanks containing one liquid and foam
The top process connection of the bypass chamber must be above the maximum level of
liquid.
The bottom process connection of the bypass chamber must be below the lowest measured
level of liquid.
Installation next to tanks containing more than one liquid
The top process connection of the bypass chamber must be above the maximum level of
liquid.
The bottom process connection of the bypass chamber must be below the lowest measured
level of liquid.
Additional process connections are necessary for the liquids to circulate freely along the
length of the bypass chamber.
3.5.5 Wall support for the remote version
1 Use marks on the wall to help you put the wall support in the correct position. For more data,
refer to
Dimensions and weights
on page 116.
2 Use equipement and tools that agree with health and safety regulations and good engineering
practice.
3 Make sure the wall support is correctly attached to the wall.
Figure 3-20: Wall support for the remote version (attached to the remote converter)