17. IGNITION SYSTEM
17-5
GRAND DINK 25 0
CDI UNIT
RESISTANCE INSPECTION
Measure the resistance between the terminals.
Replace the CDI unit if the readings are not
within the specifications in the table below.
Unit: W
(+)
(-)
L/Y
B/Y
G/GR
G/W
B/W
G/B
V/R
V/B
V/G
G
L/Y
67~125KW
36~67KW
110~200KW
36~67KW
36~67KW
B/Y
11~22MW
11~22MW
0.5~2 KW
11~22MW
11~22MW
11~22MW
11~22MW
G/GR
G/W
67~125KW
36~67KW
110~200KW
36~67KW
36~67KW
B/W
11~22MW
0.5~2 KW
11~22MW
11~22MW
11~22MW
11~22MW
11~22MW
G/B
V/R
36~67KW
36~67KW
72~133 KW
2~5 KW
2~5 KW
V/B
110~200KW
110~200KW
72~133 KW
72~133 KW
72~133 KW
V/G
36~67KW
36~67KW
2~5 KW
72~133 KW
0.1~1W
G
36~67KW
36~67KW
2~5 KW
72~133 KW
0.1~1W
Due to the semiconductor in circuit, it
is necessary to use a specified tester
for accurate testing. Use of an
improper tester in an improper range
may give false readings.
In this table, “Needle swings then
returns” indicates that there is a
charging current applied to a condenser.
The needle will then remain at “
unless the condenser is discharged.
L/Y
G/GR