6.2.3 Testing
(1) Press the TEST BUTTON
Operating time of RCD is displayed on LCD. At Auto Ramp,
operating current value of RCD will be displayed.
● × 1/2.................The Breaker should not trip.
● × 1.....................The Breaker should trip.
● × 5.....................The Breaker should trip.
● DC..................... The breaker should trip.
Auto Ramp( ).. The Breaker should trip. Check Trip Out Current.
(2) Press the 0°/180°switch to change the phase and repeat step(1).
(3) Change the phase again and repeat step (1).
Be sure to return the tested RCD to the original condition after the
test.
MAKE SURE TO KEEP CLEAR OF EARTHED METAL DURING THE
OPERATION OF THESE TESTS.
Note:
If the RCD does not trip, the tester will supply the test current for a
maximum of 1000ms on the X1/2 and X1 ranges. The fact that the
RCD has not tripped will be evident because the P- N and P- E LEDs
will still be on.
If "I⊿n" setting is grater than the rated residual current of RCD, RCD
will trip and "no" may be displayed on LCD.
If a voltage exists between the protective conductor and earth, it may
influence the measurements.
If a voltage exists between neutral and earth, it may influence the
measurements, therefore, the connection between neutral point of
the distribution system and earth should be checked before testing.
If leakage currents flow in the circuit following the RCD, it may
influence the measurements.
The potential fields of other earthing installations may influence the
measurement.
Special conditions of RCDs of a particular design, for example S-
type, shall be taken into consideration.
#
CAUTION
When the Uc voltage rises to UL value or greater, the
measurement is automatically suspended and "UcH" is
displayed on the LCD.