Lake Controller Operation Manual

Table Of Contents
Lake Controller Operation Manual Rev 1.5.8
Lake-enabled Amplifier Reference
261
20.9.4 Verify
After all required cable data is entered, tap VERIFY to initiate LoadSmart verication. Tap YES to conrm.
Load verication commences for all power output channels assigned to the selected Module. The channels
are muted and a sequenced sweep is issued. After the verication procedure has been conducted, the
LOAD RESULTS window appears.
Simultaneous load verication of all Lake-enable ampliers on the network can be initiated from the
GLOBAL CONTROL tab. Please refer to section 20.9.
LoadSmart verification can be initiated from the
PLM and PLM+ front panel, with a reduced set of
results displayed on the front-panel LCD. Refer to
the relevant Operation Manual for further info.
Figure 20-9: Load Verification Results
20.9.5 Settings
The set of buttons at the foot of the page allow the user to select the most convenient measurement units
for the load verication system and cable resistance calculation. The options are:
TEMPERATURE – °C or °F
CABLE LENGTH – Meters or Feet
CABLE GAUGE – AWG numbers or as mm2 cross-section