User Manual
Table Of Contents
- 14-0364 - Exhibit Cover.pdf
- GPR2 Installation Guide 98-1135.pdf
- Chapter 1: Pre-Installation 7
- Chapter 2: Index Cover Pulser Install and Operation Start Up 25
- Chapter 3: American GPR Index Cover & GPR Install 31
- Chapter 4: Rockwell GPR Index Cover & GPR Install 47
- Chapter 5: Schlumberger GPR Index Cover & GPR Install 57
- Chapter 6: Sprague GPR Index Cover & GPR Install 69
- Chapter 7: Electronic Pulser Installation 85
- Chapter 8: Dresser Roots Installation 99
- Appendix A: GPR Waterproofing 113
- Appendix B: Installation in Hazardous Locations 121
- Table 1-1. Typical Gas Meter Module Installation Tool List
- Table 1-2. American Meter Index Cover Mini Switch Kits
- Table 1-3. American Large Diaphragm Meter Dial Wheels
- Table 1-4. American GPR + Brackets Kits
- Table 1-5. Kit, GPR Installation, American Large Diaphragm, Alternative Orientation #45-1189
- Table 1-6. Kit, GPR Installation, American Large Diaphragm, Behind Index #45-1190
- Table 1-7. Kit, American Large Diaphragm Alternative Orientation GPR, #45-1193
- Table 1-8. Hardware Kit, American Large Diaphragm #45-1203
- Table 1-9. GPR Assembly w/ Universal Bracket #45-1185
- Table 1-10. GPR Cover Mounting Kit #45-1042
- Table 1-11. Rockwell Large Diaphragm Meter GPR Index Cover Kit
- Table 1-12. Rockwell Large Diaphragm Meter GPR Dial Wheel
- Table 1-13. GPR Installation Kit for Rockwell 750 Large Diaphragm Meter #45-1186
- Table 1-14. Kit, Rockwell Large Diaphragm Index Cover Hardware #45-1169
- Table 1-15. GPR Assembly w/ Universal Bracket #45-1185
- Table 1-16. Schlumberger Large Diaphragm Meter GPR Index Cover Kit
- Table 1-17. Schlumberger Large Diaphragm Meter GPR Back Mount Wheel
- Table 1-18. Schlumberger Large Diaphragm GPR Kit #45-1187
- Table 1-19. Kit, Schlumberger Large Diaphragm Index Cover Hardware # 45-1171
- Table 1-20. GPR Assembly w/ Universal Bracket #45-1185
- Table 1-21. Sprague Large Diaphragm Meter GPR Kit
- Table 1-22. GPR Dial Wheels
- Table 1-23. GPR Installation Kit for Sprague Large Diaphragm Meters #45-1188
- Table 1-24. Sprague Large Diaphragm Index Cover Hardware Kit #45-1114
- Table 1-25. GPR Assembly w/ Universal Bracket #45-1185
- Table 1-26. Rotary Gas Meter Module Installation Tool List
- Table 1-27. GPR Rotary Meter Cables
- Table 1-28. GPR Installation Components for Rotary Gas Meters
- Table 1-29. GE AMR Adapter Kit
- Table 1-30. Gridstream American Residential Module
- Table 1-31. Index with Consumption Pointers Removed
- Table 2 - 1. Single Form-C Volume Wiring Definitions
- Table 7 - 1. Definitions
- Table 7 - 2. Single Form-A Volume Input Definitions
- Table 7 - 3. Two Form-A Volume Inputs Wiring Definitions
- Table 7 - 4. Two Form-A and Alarm Wiring Definitions
- Table 8 - 1. 01-1337 Index Parameters
- Table 8 - 2. M120-1 Dial Wheel and Seals Hardware Kit #45-1219
- Table 8 - 3. American Index, Pointers Removed, GE AMR (Kit #45-2400)
- Table 8 - 4. LED Startup Patterns
- Table B - 1.
Landis+Gyr Chapter 7 - Electronic Pulser Installation
Installation Guide 98-1135 Rev AB 97
Start the GPR Operation In Install Mode
By now, the GPR should be fully mounted without it's cover.
The GPR module, as received from the contract manufacturer, should have the correct Network
LAN ID and CRC numbers already configured. The GPR, when installed for the first time, will start
operation in Install Mode. Install Mode is a temporary operation mode during which the GPR
initiates the first network synchronization, and performs auto-registration to Command Center. To be
able to sync to a network the GPR must have the same CRC number as that of the Network. During
auto-registration the GPR requests for operation and meter specific configurations from Command
Center. When the new configuration data is obtained, the GPR reconfigures itself, reboots, and then
changes operation to Normal Mode.
Once the GPR is properly mounted and connected to the pulser, it is ready for operation to start. To
start the GPR in Install Mode follow the procedure below.
1. The sensor cable should be installed before the battery connection to avoid false counts at
startup.
2. Apply dielectric grease compound to the battery connector. See Appendix A
, GPR
Waterproofing for more information.
3. Apply power to the module by making the battery connection.
4. Remove the foam between the battery and the PCB and discard it.
5. Observe the LED on the module for proper start up. Shortly after power is applied the LED will
flash once every 5 seconds for 60 seconds to indicate to the installer that the module is in
Installation Mode, and is operating normally. If an error is encountered, the LED will flash twice
per second to indicate there is an error and continue flashing until power is disconnected.
6. If the module started operation correctly, mount the cover as shown in the next 3 steps.
7. Arrange the GPR Pulse Input and Battery Interface cables as shown in Figure 7 - 12. The cables
must not interfere with or block the GPR antenna.
7
CHAN B COM, Channel
B common
WHITE/BLUE K2 Common
8 N/C N/A N/A Not Applicable
9
CHAN B TAMPER TEST,
channel B tamper test
Brown Y2 Tamper Test
10
ALARM (A+), positive
alarm
WHITE/BROWN A+ No Connection
11
ALARM (A-), negative
alarm
GREEN A- No Connection
Table 7 - 4. Two Form-A and Alarm Wiring Definitions
GPR 19-2331 Cable Pulser Output Connector
GPR Sensor
Connector Pin #