symmetric top beam as shown:
Position the offside column at the designated chalk location.
Lift the top beam to its high position, and use four M12
bolts, washers and lock nuts to fix it with the columns (as
shown in Fig.12). When installing the top beam, ensure the
above micro switch support bracket adjacent to the power
side column. In Fig12:The symmetric top pulleys are to be
installed at position 1
1″,asymmetric top pulleys are to be
installed at position 2
2″.
Note:
Since the offside column is not fixed to the ground,
you must operate carefully to avoid the falling of
the column.
Fig. 12