10.2.5 Install the offside column
Install the offside column as the procedures in10.2.3.
10.2.6 Install and adjust the balancing steel cables
Raise the two carriages to the safety locking position;
make sure the two carriages are of the same height
from ground. for TLT240SC models, route the steel
cables as Fig. 13 shows .
Adjust the tension of cables through the adjustment
nuts on each end of steel cable. The steel cables
should be tight in equal tension. Each steel cable
should be ensured in the pulley when adjusting tightly,
otherwise the steel cable will be damaged.
Note
Before operating the lift, re-check the
balancing steel cables and ensure they are not
crossing or wrongly installed. Ensure the steel cables
still in the pulley.
Fig.13
The two steel cables shall be adjusted to
certain uniform tension to ensure the two
carriages are moving synchronously.
10.2.7 Install the power unit and hydraulic lines
Use two M10 bolts and washers to fix the power unit
(as shown in Fig. 14). for TLT240SC models, install
the hydraulic line as shown in Fig.14 and tighten all
the fittings to prevent oil leakage.
Fill the reservoir with hydraulic oil (oil capacity of 10L).
Operate carefully to avoid dust and other pollutants
mixed with the hydraulic oil.
Note
Clean the impurities in the hydraulic line
and remove the protective plug from the
hydraulic cylinder.
When the hydraulic hose installation needs
to go through the column, ensure the
hydraulic hose won’t touch any movable
parts inside the column
During the installation, rubber cushions
must be added between the hydraulic
station and the installation plate