Product Manual

22
SYMETRIC OVERHEAD BEAM INSTALLATION
Lift the overhead beam to the level of the column tops and use the fasteners to
attach it to the upper columns and the transitional brackets. If you are installing for
a Symmetric configuration the column mounting bolts must be aligned as show
below.
IMPORTANT: HAND TIGHTEN THE BOLTS ONLY AT THIS TIME
The drawing below outlines where the overhead beam bolt positions are used on
the transitional brackets
Figure 6
When installing the overhead beam, ensure the microswitch support (It is the U-
shaped bracket welded to the bottom of the overhead beam) is adjacent to the
power side column location. This will allow you to route the microswitch cord
through the end of the overhead beam and down the outside of the power unit
column.
Note:
Since the idler column is not secured to the floor by the bolts at this stage,
be careful to not move the idle column as it is not anchored to the floor.
SLAVE SIDE COLUMN INSTALLATON
Measure the distance between the top and bottom of each column to insure the
columns are parallel to each other. Finish leveling, anchor bolt drilling, shimming if
needed and the anchor bolt installation of the slave side column at this time as
instructed above for the power unit column..
After the slave side column has been installed proceed back to
the overhead beam section and tighten all connection bolts and
nuts of the overhead beam and the transitional brackets before
proceeding to the next section.