9. Level the shower and set plumb. If the oor is not level, it
will require the use of shims to level the shower. See Picture
5 If shims are required, they should be placed no more
than 6 inches apart to provide proper support. DO NOT
SHIM THE UNIT MORE THAN 1/8”. If the shower requires
more than 1/8” shim adjustment, the shower will need to be
pulled out and the oor will need to be leveled. Insure the
drain is lined up in the appropriate areas.
10. Secure the shower to the framing members through the
anges using 6D galvanized screws on 8” centers.
11. Cut a 2 x 4 member of 10” to place directly over the
drain area. Cut a 2 x 4 member to extend from the ceiling
to the 10” wooden block on the drain area. Protect the
shower surface by placing a towel under the wooded block.
12. Place the brace from the ceiling to the 10” piece of
wood. This should be a tight t. See Figure 5 continuous bead
of Liquid Nails Construction adhesive.
13. Repeat steps 11 through 12, for the threshold, pressing it
down to make complete contact with a continuous bead of
100% silicone adhesive.