Task
11.3
Install floor cover trim
11.4
Determine location for OCP and install OCP mounting bracket
11.4
Install two additional OCP mounting brackets for barrier belt
11.5
Install top outer radome angle brackets
11.9
Install antenna masts
11.10
Route antenna mast cables and connect to ISUs
11.11
Clean cosmetic mast wrap with ESD wipes and install
11.12
End cap top bracket
11.13
Install entrance/exit covers
11.14
Install vibration control pads
11.15
Peel outer radome scratch guards and clean inner side with ESD wipes
11.16
Install outer radomes and clean outer side with ESD wipes
11.17
Install outer radome bracket supports
11.17
Install middle cover brace bracket U-clips
11.18
Install outer radome bracket retainers
11.19
Tighten outer radome screws
11.20
Verify antenna operation
11.21
Install housing brace brackets
11.22
Route power cable/other cables; separate and cable-tie if necessary
11.23
Install top down power [OPTIONAL] if required.
11.24
Install power input box
11.25
Install router [optional] refer to 8000-23712-IP
11.26
Install remote OCP [optional]
11.27
Install roof
11.28
Install clip-on panel nuts in top side covers, then install top side covers
Error! R
eference
source
not
found.
Install blank plate and cable pass-through hole/grommet
11.31
Install middle OCP cover
11.32
Install plain middle cover
11.33
Install middle covers for barrier belt
11.34
Install upper/lower cover with switch/power input
11.35
Install plain upper/lower covers
11.36
Install top entrance/exit covers
11.37
Install barrier belt assembly
11.38
Install OCP mount pole and OCP
11.39
Install label kit
11.40
Install system mounted Resolution Station [optional]
11.41
Install inner radome top angle rails
11.42
Install inner radome base flange support brackets
11.43
Peel inner radome scratch guards and clean with ESD wipes
11.44
Install inner radome edge support brackets
11.45
Install inner radomes
11.45
Tighten inner radome screws
11.46
Install ceiling
11.47
Install ramp supports and ramp assemblies
11.48
Install floor side panels and center panel