User's Manual

Page 22
GROUND
JOINT
UNION
DRIP LEG
MANUAL
MAIN SHUT-OFF
VALVE
GROUND
JOINT
UNION
DRIP LEG
MANUAL
MAIN SHUT-OFF
VALVE
GROUND
JOINT
UNION
DRIP LEG
MANUAL
MAIN SHUT-OFF
VALVE
Horizontal Applications
Possible Gas Piping Configurations
Horizontal Application
Left-Side Air Discharge
Horizontal Application
Right-Side Air Discharge
NOTE - BLACK IRON PIPE ONLY TO BE ROUTED INSIDE OF CABINET
FIELD
PROVIDED
AND INSTALLED
FIGURE 26
Leak Check
After gas piping is completed, carefully check all piping
connections (factory- and field-installed) for gas leaks. Use
a leak detecting solution or other preferred means.
NOTE - If emergency shutoff is necessary, shut off the main
manual gas valve and disconnect the main power to the
furnace. The installer should properly label these devices.
CAUTION
Some soaps used for leak detection are corrosive to
certain metals. Carefully rinse piping thoroughly af
ter leak test has been completed. Do not use
matches, candles, flame or other sources of ignition
to check for gas leaks.
The furnace must be isolated by closing its individual
manual shut‐off valve and disconnecting from from the gas
supply system during any pressure testing of the gas sup
ply system at pressures greater than 1/2 psig (3.48 kPa, 14
inches w.c.).
IMPORTANT
When testing pressure of gas lines, gas valve must
be disconnected and isolated. See figure 27. Gas
valves can be damaged if subjected to pressures
greater than 1/2 psig (3.48 kPa, 14 inches w.c.).
MANUAL MAIN
SHUT-OFF VALVE
WILL NOT HOLD
NORMAL TEST
PRESSURE
CAP
ISOLATE
GAS VALVE
FURNACE
FIGURE 27
1/8 NPT PLUG
Electrical
ELECTROSTATIC DISCHARGE (ESD)
Precautions and Procedures
CAUTION
Electrostatic discharge can affect elec
tronic components. Take precautions
to neutralize electrostatic charge by
touching your hand and tools to metal
prior to handling the control.
The unit is equipped with a field make-up box on the left
hand side of the cabinet. The make-up box may be moved
to the right side of the furnace to facilitate installation. If the
make-up box is moved to the right side, clip the wire ties
that bundle the wires together. The excess wire must be
pulled into the blower compartment. Secure the excess
wire to the existing harness to protect it from damage.