Bathtub Installation

FREESTANDING BATHTUB
INSTALLATION AND MAINTENANCE
Note: If you purchased a brushed nickel trim kit, it must be installed before
installing the bathtub (brushed nickel trim not available on all models).
Warning: Due to the rough handling during shipping or on the job
site, do not install this product until a thorough inspection and water test
has been completed.
Check bathtub for correct model and size. Carefully inspect the tub
for any damage (i.e. chips, scratches, cracks). If at any point during the
pre-installation inspection and water test, you discover a problem with the
bathtub or piping system, do not install the unit and contact us
immediately.
All preinstalled parts must be checked and retightened before
installation.
INSTALL BATHTUB
1. Clean, level, and prepare the floor for installation.
2. Determine the location of the drain pipe on the floor by taking
measurements of the drain and waste location beneath the unit.
3. Place the bathtub in the designated space ensuring that the drain
and waste locations match with that of the tub and adjust the
balancing feet as needed, using a level.