Drain Piping Specifications
• Drain piping must have downward gradient of at
least 1/50 to 1/100; to prevent reverse flow, slope
should not be straight up and down.
• Do not damage the drain port on the indoor unit
when connecting the field-supplied drain piping.
Drain Hole
Gaps Should Not Be Present
Unit
Drain Piping
(Field Supplied)
Drain Piping Insulation
(Field Supplied)
U-Trap
B
C
A
3/4-inch Connecto
r
Field-Installed U-Trap Specifications
Figure 239:Close up of Drain Piping Connection.
Figure 240:Installing the U-Trap.
To prevent leaks cause by a block in the intake air lter, install a U-Trap.
A ≥ 2-9/16 inches
B ≥ 2C
C ≥ 2 x SP
SP = External Pressure in. WG
Example:
External Pressure= 0.4 in WG
A ≥ 2-9/16 inches
B ≥ 1-7/12 inches
C ≥ 19/24 inches
Drain Access Hole
Air Filter Cover
Main Drain with Suitable Trap. (Field-Supplied
Trap with Sufficient Depth Can Be Used.
Standard Size P-Traps Cannot Be Used.
Supplementary Drain with a
Proper Trap (Field Supplied Kit
Can Be Used)
Figure 241: Vertical Primary and
Secondary Drain Layout.
Figure 242: Horizontal Primary and
Secondary Drain Layout.
Refrigerant Piping Insulation
Field-installed vapor and liquid refrigerant piping lines must be
properly and completely covered in insulation (up to the indoor
unit piping connections) and must comply with federal, state,
and local requirements. Any exposed piping may generate
condensate or will cause burns if touched. Insulation for this
field-installed refrigerant piping must have a minimum heat
resistance of 248°F.
If the indoor unit is installed and is operated at an extended
period in a highly humid environment (dew point tempera-
ture >73°F), however, condensate will form. To prevent this
phenomenon, install adiabatic glass wool insulation with a
thickness of 7/16 to 13/16 inches thick. Also, install glass wool
insulation on all indoor units that are located in the ceiling
plenum.
Drain Piping Insulation
Drain piping insulation must be 7/32 inches thick, minimum.
Insulating the Refrigerant and
Drain Piping
Connection for Liquid Piping
Refrigerant Piping
Insulation (Field Supplied)
Connection for Vapor Piping
Insulation Zip Tie (Field Supplied)
Refrigerant Piping Insulation (Field
Supplied)
Figure 243:Close Up of Refrigerant Piping Connection Insulation.
Gaps Should Not be Present
Overlap Piping Insulation
Refrigerant Piping Insulation (Field Supplied)
Insulation Clip (Field Supplied)
Refrigerant Piping Insulation
(Field Supplied)
Figure 244: Insulating the Refrigerant Piping and Refrigerant Piping
Connections.
Ensure all piping is insulated. Exposed piping can cause
burns if touched.
Due to our policy of continuous product innovation, some specications may change without notication.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
178 | VERTICAL-HORIZONTAL
Multi F and Multi F MAX Indoor Unit Engineering Manual
MULTI
F
MAX
MULTI
F