Engineering Manual

Table Of Contents
Installing the Ducts
Use more than ten (10) screws to securely attach the supply ducts to the
unit. To prevent air leaks, seal around the duct opening before the duct is
secure.
To prevent vibration transmission, install flexible connectors between ducts
and the unit. The flexible connectors must be made of a heat-resistant
material at the discharge connection if an electric heater is installed.
Duct work must be insulated and covered with vapor barrier when routed
through unconditioned spaces. Include enough insulation to prevent
condensate from forming on the ducts.
It may be necessary to add internal acoustical insulation lining for a metal
duct system if it does not include a 90° elbow and ten (10) feet between the
main duct and the first branch.
Fibrous glass ducts could be used as a substitute if built and installed in accordance with the most recent edition of the Sheet Metal and
Air-Conditioning Contractors’ National Associate (SMACNA) standard.
Also, fibrous duct work and acoustical insulation lining must also follow National Fire Protection Standard 90A or B as tested by UL
Standard 181 for Class 1 air ducts.
VERTICAL-HORIZONTAL INDOOR UNITS
Installation and Best Layout Practices
>10 Screws
(M4*25L)
Figure 230:Securing the Ducts to the Unit.
Installing the Drain System
General Specifications
To prevent property damage, optimize drain system performance by installing both a primary and secondary drain line, and properly size
the condensate traps.
The primary and secondary drain line must be trapped to allow proper drainage of condensate water. If the secondary drain line is not used,
it must be capped.
Do not block the filter access panel when installing the condensate drain piping. Prime the primary and secondary condensate traps after
running both to the drain pan.
If the unit is installed above an inhabited space, add a field-supplied external condensate pan that runs underneath the entire frame (to
prevent damage from overflow). The additional external condensate line should run from the unit to the external condensate pan.
Drain all generated condensate from the external condensate pan to an appropriate area. Install a trap in the condensate lines as near to
the indoor unit coil as possible.
All condensate should be drained from the external condensate pan to some noticeable area.
To prevent overflow, the outlet of each trap should be positioned below its connection to the condensate pan.
All traps should be primed, insulated, and leak
tested if located above an inhabited space.
Use a 3/4-inch PVC male pipe thread fitting at
the condensate pan connection. Tighten gently.
Point the drain hose down for easier flow.
Do not just use the pipe joint or PVC / CPVC
piping on the indoor unit drain line connections.
Use only Teflon tape.
Design the drain system to plan for winter opera-
tion (condensate line may freeze up if conden-
sate does not properly drain away).
Field-Supplied
Drain Pan
Drain Piping
Field-Supplied
Drain Pan
Drain Piping
Figure 231:Vertical Installation Drain System. Figure 232:Horizontal Installation Drain System.
VERTICAL-HORIZONTAL | 167
Vertical-Horizontal Air Handling
Due to our policy of continuous product innovation, some specications may change without notication.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
MULTI
F
MAX
MULTI
F