Multi F Outdoor Condenser Installation Manual

34
MULTI F / MULTI F MAX Outdoor Unit Installation Manual
Due to our policy of continuous product innovation, some specifications may change without notification.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
MULTI
F
MAX
MULTI
F
LATS Generates a Complete Project Report
LATS software also generates a report containing project design parameters, cooling and heating design data, system component perfor-
mance, and capacity data. The report includes system combination ratio and refrigerant charge calculations; and provides detailed bill of
material, including outdoor units, indoor units, control devices, accessories, refrigerant pipe sizes segregated by building, by system, by pipe
size, and by pipe segments. LATS can generate an Excel GERP report that can imported into the LG SOPS pricing and ordering system.
Proper Design to Install Procedure
LG encourages a two report design-to-install-proce-
dure. After the design engineer determines building
/ zone loads and other details, the engineer opens
the LATS program and inputs the project’s infor-
mation. When the design is complete, the “Auto
Piping” and “System Check” functions must be used
to verify piping sizes, limitations, and if any design
errors are present. If errors are found, engineers
must adjust the design, and run Auto Piping and
System Check again. When the design passes the
checks, then the engineer prints out a project “Shop
Drawing” (LATS Tree Diagram) and provides it to the
installing contractor. The contractor must follow the
LATS Tree Diagram when building the piping system, but oftentimes the design changes on the building site:
Architect has changed location and/or purpose of room(s).
Outdoor unit cannot be placed where originally intended.
Structural elements prevent routing the piping as planned.
Air conditioning system conflicts with other building systems (plumbing, gas lines, etc.).
The contractor must mark any deviation from the design on the Shop Drawing, including as-built straight lines and elbows. This “Mark Up”
drawing must be returned to the design engineer or Rep, who must input contractor changes into the LATS file. (Copy the original LATS soft-
ware file, save and rename as a separate file, and modify all piping lengths by double-clicking on each length and editing information.) Like
the shop drawing, the Auto Piping and System Check must also be run on this new “As Built” drawing. The design engineer or Rep must then
provide the final As Built file to the contractor. The Mark Up version must be compared to the As Built version for:
Differences in pipe diameter(s). If incorrect diameters have been installed, the piping must be changed out. If pipe diameters have changed,
check to see if Y-Branches will also need to be changed.
Changes to outdoor unit and indoor unit capacities. Capacities changes will impact line length changes.
Additional refrigerant charge quantity (“Trim Charge”). Trim charge will change if piping lengths and diameters change. The As Built version
must reflect installed piping lengths to ensure correct trim charge.
All documents submitted by the contractor, as well as the Shop Drawing and the As Built Drawing files must be provided for commissioning
purposes. Model and serial numbers for all system components must also be submitted. If the steps previously detailed are not followed,
and all documents are not provided to the commissioning agent, the project runs the risk of not being commissioned and voiding any limited
warranty LG offers on the equipment.
LG AIR CONDITIONER
TECHNICAL SOLUTION (LATS)
Contact your LG representative for the vest software program for your application.
Figure 23: Example of a LATS Tree Diagram.