Recommendations:
Warnings:
• Please follow the important LC3 mounting guidelines.
• LC3 is for use in push or pull applications, cable outlet from smallest profile (top) or biggest profile (bottom). See top and bottom plate dimensions.
• When washing according to IPX6 parameters please notice that the large profile of the LC3 column must be placed upwards (bottom up).
• We recommend making a functional test of the application with all accessories connected before putting it into operation.
• Regular cleaning is recommended to reduce bacteria and increase the hygiene level
• Intended for indoor use only
• Not intended for use in harsh environments like e.g. pool environment, marine environment and agriculture buildings with ammonia vapors.
• Always check correct assembly after mounting and service to ensure that the cable locks are mounted.
• Ensure that the cable cannot be squeezed, pulled or subjected to any other stress or damages.
• LC3 is heavy (more than 10 kg). To avoid personal injury and product damage, DO NOT DROP!
• Take special precautions concerning 3rd party interfacing. Please contact LINAK for further information.
• Do not exceed the max. pull load specified on the label.
• Do not add dynamic load when changing between pull and push.
• Do not adjust anything during movement or while connected to mains, it can cause personal injury.
• To avoid cable interruption and actuator defects make a proper cable installation and inspect regularly for wear, damage and jarring sound.
Defective parts must be replaced.
• After service inspection, the application must be tested for correct functionality before it is put into operation, to avoid misalignment between
two columns moving in parallel.
• LINAK recommend using a safety nut in medical applications! LC3 has safety nut as standard.
• Do not loosen any screws on the LC3, this can cause collapse of the column!
• LINAK recommends making regular measurement of Class 1 protective ground conductivity in the application to avoid a disconnected
grounding cable. If there are worn out or defect parts, the complete LC3 must be replaced.
• Interconnecting cables must remain plugged in during cleaning to prevent the ingress of water.
The LP2 range of vertical lifting columns is ideal where vertical positioning of
substantial loads is required.
Usage:
• Ambient temperature: +5
o
to +40
o
C
• Duty cycle: 2/18; 2 minutes continuous use followed by 18 minutes not in use
• LP2 is compatible with CB8, CB12 or CB14
• Approvals: IEC 60601-1
ANSI/AAMI ES60601-1
CAN/CSA-C22.2 No. 60601-1
4. LP2 (DESKLINE
®
MEDLINE
®
CARELINE
®
TECHLINE
®
)
Recommendations:
• Cleaners and disinfectants must not be highly alkaline or acidic (pH value 6-8)
• Depending on the choice of control box, it is possible to operate 2 lifting columns in parallel and save up to 3 memory positions.
• If parallel drive or memory function is required, the lifting column has to be ordered with reed switch.
• If LP2.2 is used as a single column, twisting of the column is a possible effect that can occur during the lifetime of the column.
• The column is not constructed to withstand twisting in an application.
• The column must only be mounted with the largest profile uppermost.
Warnings:
• The column can only be loaded with the maximum bending moment over the first 80% of the stroke.
• Above this 80% figure, the max. bending moment will be reduced to 50%.
• The column must not be used in pull.