Pre-shift checks
Functional test of the Static Unit
The functional test must be completed regard-
less of the industrial truck component
configuration. When using the Truck Unit
Small, per-
form the following steps as well.
The functional test checks the signaling zones
that have been set and any responses that
have been set on the industrial truck.
• Switch on the industrial truck. The Truck
Unit switches on.
• Check the operational readiness of the
Static Unit.
The "operating status" LED must flash green.
• Drive the industrial truck to the signaling
zone. During this process, the driver
monitors the Truck Unit and any
responses that have been set on the
industrial truck. A second person
monitors the Static Unit (figure
LSG_0059).
Fault messages and irregularities on the Truck
Unit or the Static Unit during the test are not
permitted.
• If necessary, have the signaling zones
and the truck settings set up again by the
service partner.