Installation Instructions
TRIM & FASCIA 190, 440, 540 & 2000 SERIES
APPLICATION
INSTRUCTIONS
• Properly installed ashing materials will help direct water away from
common water collecting areas.
• All ashing material shall be metal or another durable material that
under normal outdoor environmental conditions will last for a period of
not less than 50 years.
• All ashing materials must have a minimum 4 inch upper leg. Add a
4 inch wide adhesive ashing to ashing legs less than 4 inches.
• Properly integrate ashing with the secondary WRB. Use housewrap,
ashing tape, kick-out ashing, step ashing, Z-ashing, drip edge, gutters
or other items as needed to maintain the counter-ashing principle.
• Install kick-out ashing to direct the water into the gutter.
(See diagram 3a)
• Install step ashing that has a minimum 4 inch upper leg.
(See diagram 3a)
• Maintain a minimum 1 inch clearance between the end of the gutter
and the adjoining wall to allow for proper maintenance of the siding.
(See diagram 3b)
• Do not extend the siding or trim into the kick-out ashing or gutter.
• Prime and paint ALL exposed cut edges of siding and trim.
PREPARATION
WATER RUN-OFF CONTROL
• FASTENERS: Minimum 8d (0.113 inch diameter shank), hot-dipped galvanized nail with a 0.270 inch diameter head. Apply and treat
nailing errors as specied by these instructions. (See diagram 3c)
• SEALANT: Use an exterior-quality, non-hardening, paintable sealant. Use Class 25 or higher exterior sealant meeting the ASTM C920 Stan-
dard for Specication for Elastomeric Joint Sealants. Follow the sealant manufacturer’s instructions for application.
• PAINT: Exterior-quality 100% acrylic latex paint, specially formulated for use on wood and engineered wood substrates, is highly
recommended. Semi-gloss or satin nish oil or alkyd paints are acceptable. For at alkyd paint, please check with the coating manufacturer
for their recommendations for use on composite wood siding.
3a
GENERAL APPLICATION EQUIPMENT
3b
3c
1” min.
clearance
Kick-out
ashing
1” min.
clearance
4” min.
step ashing
3