User's Manual
DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r 
555-233-115 
Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-21Add the Fiber Optic Cable 
6
Figure 6-12. Dress the Cable
15. If a circuit pack was removed to access 2 open slots (from 
‘‘Cabinet 
Preparation’’ on page 6-10), replace the circuit pack into its original slot.
16. Close the front door.
17. Discard the pass-thru tool.
Test the Installation
1. Login to the management terminal.
2. Administer the system by referring to the ATM section of the 
Installation 
and Test for Adjuncts and Peripherals
.
3. Type 
list configuration all
 and press 
Enter to determine if the new circuit 
pack appears in the correct slot and that there are no circuit pack 
conflicts.
lcda4fop RPY 02139
8