User's Manual
DEFINITY ECS Release 8.2 Maintenance for R8.2csi 
555-233-119  Issue 1
April 2000
Maintenance Commands 
2-379test sys-link 
2
Action/ 
Object Qualifier Qualifier Description Permissions Defaults
Feature
Interactions
test 
sys-link
location
current
faulted
short
long
repeat 
number
clear
schedule
Port location associated with the system 
link.
Current hardware path tested
Tests the hardware path of the system 
link as it was constituted when a fault 
last caused the link to go down.
Option for a brief series of 
nondestructive diagnostic tests.
Option for a longer, more 
comprehensive series of both 
destructive and nondestructive 
diagnostic tests.
How many times each test in the 
sequence is repeated (1-100)
This option causes the test sequence 
(short or long) to repeat until the alarm (if 
any) is cleared or a single test in the 
sequence fails.
1
Command is validated and then a 
scheduling form displays to schedule 
execution of the command. The 
command is then placed in the 
command queue and is executed at the 
specified time. The information 
displayed by the command is sent to the 
system printer instead of the screen.
2
Examples:
test sys-link 2e0201 current schedule
test sys-link 2e0201 faulted r 10
1 If no alarms are registered against the maintenance object then the test sequence is run only once. The
 long 
clear
 option forces a clear of all alarms if no errors are encountered during testing. The 
short clear
 option only 
clears alarms pertinent to tests in the short sequence.
2 Refer to the Report Scheduler and System Printer feature specification for more details.
init
inads
craft
none