Installation Guide

7
6"
6"
C
1.3
Check me!
D
2
STEP Installing the bathtub
Install the bathtub (13) pushing it completely against
the back studs. Center the bathtub left to right inside
the alcove leaving equal spacing on both sides.
13
Leveling the bathtub is
critical for wall alignment
Verify that the bathtub is completely level on all sides.
Conrm that the drain pipe is centered.
We recommend that a plumber completes the drain
pipe connection.
Centering the bathtub left to right is
critical for side wall installation.
13
Top view
Flush
2.1
Check me!
2.2
Check me!
2.3
Check me!
Studs
Connect plumbing (drain, overow, faucets, etc.) ac-
cording to local standards and to general rules in the
bathtub installation guide. Make sure that all joints are
waterproof.
2
Remove clear plastic lm on the bathtub. Use
cardboard on the bathtub oor as protection until
the installation is complete.
Cut out an approximate 6" x 6" opening around
the drain center outlined by measurements C and
D. See image to the right and the chart above. We
recommend that a plumber completes the drain pipe
connection.