Owner's Manual

24 Part Number: 000013325 Rev 02 6/17
Installation Section 2
Step 6 Connect Wiring to Condensing Unit or Remote
Condenser and Ice Machine Head Section.
ICVD REMOTE CONDENSING UNIT
Attach wiring to terminal strip in control box of condensing
unit and control board in ice machine head section. Match
wire labels to connections see “ICVD Interconnecting Wiring
on page 15 and “ICVD Transformer Wiring” on page 15.
REMOTE CONDENSER
The remote condenser voltage matches the ice machine
head section voltage see “Remote Condenser Wiring” on
page 15.
Step 7 Leak-Check the Refrigeration System.
A. Connect power to the ice machine head section - Do
not connect power to the ICVD condensing unit.
B. Press the power switch and energize the ice
machine for 60 seconds to equalize pressures.
C. Disconnect power to the ice machine head section.
D. Leak-check lineset connections, S trap and all
factory joints in head section and condensing unit.
E. Connect power to the ICVD condensing unit and
allow system to pump down.
Step 8 Insulation Requirements
To prevent condensation, the entire suction line,
including the shutoff valve, must be insulated.
All insulation must be airtight and sealed at both ends.
The following insulation requirements prevent condensation
at 32°C (90° F) ambient temperature and 90% relative
humidity. If higher humidity is expected, increase insulation
thickness:
Suction Line Liquid Line Min. Insulation Thickness
19 mm
3/4 inch
13 mm
1/2 inch
Suction Line - 13 mm (1/2 inch)
Liquid Line - 7 mm (1/4 inch)
16 mm
5/8 inch
10 mm
3/8 inch
19 mm
3/4 inch
16 mm
5/8 inch
Suction Line - 19 mm (3/4 inch)
Liquid Line - 7 mm (1/4 inch)
Step 9 Insulation for the Suction Shutoff Valve
The pre-formed insulation for the suction shutoff valve is
located in the plastic bag taped to the water curtain.
Position Bin Thermostat Probe
Ice Beverage Models Only
The thermostat probe must be moved from the shipping
position to the ice-making position.
The bin thermostat probe must be rotated down to
enable ice contact and proper operation.
Verify probe wire does not interfere with the water
curtain.
The control is preset and does not require programming.
1. Loosen thumbscrew securing probe.
2. Rotate the probe from horizontal to vertical position.
3. Tighten thumbscrew to secure probe.