9. Once the membrane element orientation has been
determined, install a housing adapter into the end of
the permeate tube with a gradual twisting/turning
motion. Install the plug adapter into the end of the
permeate tube that will be closest to the lower end of
the housing (e.g., nearest the floor).
10. Insert the membrane element in the housing
(including U-cup seal and housing adapter) with a
smooth and gentle twisting motion. Ensure that the
housing adapter (installed in Step 9) sits at the bottom
of the housing.
S
3/4" CLAMP GASKET
R
4" CLAMP GASKET
R
S
P
CONCENTRATE
N
FEED
M
PERMEATE
L
PERMEATE TUBE
K
MEMBRANE ELEMENT
H
LTD
J
PLUG
G
PLUG/ADAPTER
F
CONCENTRATE SEAL
E
O-RINGS
D
INTERCONNECTOR
C
INTERBANK PLUG
O-RING
B
INTERBANK PLUG
A
LEGEND
ENDCAP W/ LTD
F
G
F
E
D
C
B
A
L
K
J
H
Figure 5.10 Cross Sectional View Membrane Element and Housing Flow
11. For membrane OS1229398, insert an interconnector
into the permeate tube located closest to the open
end of the housing. For membrane 3027262 connect
the adapter to the permeate tube.
12. Install the end cap and affix the closure device.
13. Reconnect the permeate tube to the permeate
manifold.
14. Repeat for other membrane elements as necessary.
15. Before putting the machine back into normal
operation, run the permeate and concentrate streams
to drain for at least 1 hour. This is done to ensure that