Installation Guide

© Metal Sales Manufacturing Corporation / Subject to change without notice / Effective 11/14
22
1.25" Corrugated
2.5" Corrugated
CORRUGATED PANEL INSTALLATION
INSTALLING FIRST PANEL
INSTALLING CLOSURES
INSTALLING
PANEL CLIP
STEP
1
STEP
2
CLOSURE
WITH TAPE SEALANT
TAPE SEALANT
(on top of closure not shown)
CLOSURE
WITH TAPE SEALANT
ROOF PANEL
1. Apply a row of Tape Sealant across the top leg of the Eave Flashing along the width of
the building.
2. Align and place Closures over the Tape Sealant. It is critical that Closures are square to build-
ing as this will control the alignment of the panels.
(see page 16 to check building square).
3. Apply a row of Tape Sealant across the top of the Closure (Not shown for clarity).
1. Install the rst panel over the Closure to allow for desired overhang. Make sure the panel is
square to the eave and rake.
2. Fasten through panel, Closure and Tape Sealant into decking with appropriate amount of fas-
teners to meet local building code. (see fastening patterns on page 7 and 9). Fasteners must
penetrate Closures and Tape Sealant.
3. After securing panel at eave, repeat the fastening pattern at the appropriate spacing to meet
local building codes.
NOTE: -Eave, Gutter and Valley Flashings must rst be installed before panel installation can begin.
-Panels can be installed going from either left to right or right to left, looking from eave to peak.