Installation Guide

© Metal Sales Manufacturing Corporation / Subject to change without notice / Effective 11/14
23
1.25" Corrugated
2.5" Corrugated
CORRUGATED PANEL INSTALLATION
FIRST PANEL INSTALLED
INSTALLING SIDELAP PANEL
STEP
3
STEP
4
INSTALLING SECOND PANEL
RIDGE PANEL
EAVE PANEL
SINGLE BEAD
TAPE SEALANT
FASTENER
CLOSURE
FASTENER
1. Place the lapping seam of the second panel on top of previously installed panel so that panel
ends are ush at eave (see below).
2. Fasten through panel, Closure, and Tape Sealant into support with appropriate amount of
fasteners to meet local building code. (see fastening patterns on pages 7 and 9). Fasteners must
penetrate Closure and Tape Sealant.
3. After securing panel at eave, repeat the fastening pattern at the appropriate spacing to meet local
building codes.
6" Lap
1. Apply a row of Tape Sealant across and over the ribs of the rst panel about 3" from panel end.
2. Install the second panel over the rst panel and Tape Sealant with a 6" Endlap. Fasten through both
panels and Tape Sealant into support with appropriate amount of fasteners to meet local building
code. (see fastening patterns on pages 7 and 9). Fasteners must penetrate Tape Sealant.
3. After securing panel at eave, repeat the fastening pattern at the appropriate spacing to meet local
building codes.