Installation Guide

© Metal Sales Manufacturing Corporation / Subject to change without notice / Effective 6/14
20
CLASSIC RIB
®
As shown below with the number designations, install panel against the prevailing wind. Installing Wall Panels first then
Roof Panels
To minimize corrosion, siding panels should not be installed all the way to the ground.
Siding panels should lap over the foundations or splash boards at least three inches.
Make sure panels are square and plumb, to assure straight and proper alignment of the entire row of panels.
For areas with high wind considerations, closer fastener spacing may be required.
It is necessary to attach a temporary guide to the foundation to use as an alignment guide when installing siding panels.
Siphon groove side of panel must be overlapped with the non siphon groove side of the adjacent panel (if applicable) .
INSTALLATION OVERVIEW
INSTALLATION OVERVIEW
Prevailing
Winds
ANGLE BASE DETAIL
(SEE PAGE 32)
CORNER DETAIL
(SEE PAGE 30)
EAVE DETAIL
(SEE PAGE 32)
GABLE DETAIL
(SEE PAGE 31)
RIDGE DETAIL
(SEE PAGE 30)
1
PANEL ENDLAP
(SEE PAGE 29)
3
5
2
4
1
2
3
J-CHANNEL
(SEE PAGE 34)