INSTALLATION OF FORMED RIDGE
FORMED RIDGE
STILE CLOSURE OR UNIVERSAL CLOSURE
(UNIVERSAL USED ON HIP ONLY)
TUBE SEALANT
POP RIVET
STILE PANEL
FORMED RIDGE
1. Position the Formed Ridge at the peak of the roof and square with the front edge of the Formed
Rake.
2. Align the Formed Ridge so that the flanges extend down on each side of the roof equal distance.
3. Place Stile Closure under the flange on each side of the Formed Ridge.
4. Place
1
/8" Pop Rivet in the flange of the Formed Ridge so that the Formed Ridge is fastened to the Stile
panel at the top of every other rib of the panel. Do not install the last fastener until the next piece of
Formed Ridge has been overlapped with the installed Formed Ridge.
5. After all the Formed Ridge has been installed, close off the ridge at each end of the roof by placing a
Ridge Closure End Plug in the open area.
WOODSCREW XL
MOISTURE BARRIER
STILE CLOSURE
FORMED RIDGE
STILE PANEL
SIMPLE RIDGE CONDITION
STILE FORMED RIDGE CLOSURE
FORMED RAKE
POP RIVET