Instructions / Assembly

How to ErEct AccEss FrAmE
Scaffolding
by Metaltech
Scaffolding should be erected by at least two people. One
person should be knowledgeable in erecting scaffolding to
supervise the work. These step-by-step instructions are only
a general guide. The following example is based on building
a scaffolding that is 7 x 5 ft. (2.1 x 1.5 m) by 1 frame high.
Select and prepare the ground area. Place suitable sills
and make sure there are no holes under the sills. Select
the equipment you need and place it near the work
area. Put the adjustable screw jack plates on the sills
in the location that matches your scaffold dimensions.
Do not secure the bases to the sills at this step.
Adjust the nuts of the screw jack, starting at the highest
point of the ground level. The nuts at the highest ground
level should be set to 3-6 in. (7.5-15 cm) from the
top of the sill, depending on the slope. Place the rst
frame onto the base at the highest point. Connect the
rst cross brace to the frame. Allow the frame to lean
slightly forward and rest on the sill while you prepare
for the next frame to be installed.
Install the second frame onto the screw jack. Secure
the rst cross brace to the second frame.
Install the second cross brace to both frames. Next,
you need to level and plumb the scaffolding. Start at
the highest point of the scaffolding. If possible, use the
screw jack to bring the highest corner down closer to
the sill. Next, bring all four corners up to that point. If
the bottom cross braces of each frame are level with
each other, then frames should also be plumb. Install
the diagonal brace to keep the scaffolding square.
Check the level again and plumb if necessary. Fasten
the screw jack to the sills with either nails or screws.
Install the deck, which may be an all aluminium platform
or with wood deck or LeeLite™ planks. If using wooden
planks, they must extend beyond the supporting points
at least 6 in. (15 cm) but not more than 12 in. (30 cm).
Secure the deck so it cannot move.
Install the guardrail posts onto the coupling pins
seated in the top of the frames. Put a pig tail lock
through the top and bottom of each coupling pin to
avoid any separation.
Attach the guardrails to the posts on all the exposed
sides.
Install toeboards as required. The gap between the
bottom of the toeboard and the top of the platform
must not be more than 1/2 in (13 mm).
2
3
4
5
6
7
8
1 800 363-7587
www.metaltech.i nfo
RequiRements foR access fRame scaffolding
n A scaffold must be erected, altered, and dismantled by qualied workers or under the
direct supervision of a qualied person. The qualied person must ensure that the
erection is carried out properly, and that the correct components and materials are
being used.
n All equipment must be inspected before use to ensure that it is in good repair and
suitable for the intended use.
n The base must be rm and level enough to support the load of scaffolding, workers,
and materials. Sills and base plates are required on any soil or unstable ground
condition, or where any levelling adjustment is needed. The sill must be sound, rigid,
and capable of supporting the maximum loads without settlement or deformation.
n Screw jack base must be adjusted within the limits specied by the local regulation.
n The frames must be plumb and level and spaced to adequately support the loads.
n If uplift could cause the components to separate, locking pins must be used and the
components secured. Uplift might be caused by the action of wind on a secured deck
or by the leverage action of a cantilever side bracket on the scaffolding. All joints must
be pinned on rolling scaffoldings and free-standing towers.
n With a rolling scaffolding or free-standing tower, the platform height must not exceed
three times its smallest base dimension (3 to 1 rule).
n A scaffolding built above the 3 to 1 rule must be effectively guyed or secured to a
building or structure to prevent overturning. The guying of a scaffolding may require the
direction of a professional engineer.
n Guardrails must be installed on all open sides of the platform where a person could fall
a distance of 10 ft. (3 m) or more. The top rail must be placed 40-44 in. (102-112cm)
above the work surface. An intermediate rail must be placed halfway between the top rail
and the toeboard, if one is provided, or halfway between the top rail and the work
surface if no toeboard is provided.
n Toeboards must be installed on all the open sides of a platform where it is possible for
tools and or materials to roll off. The top of the toeboard must be at least 4 in. (10 cm)
above the platform. If loose materials are to be stacked above the height of the
toeboard, then the toeboard must be increased in height or mesh panels must be
installed to prevent materials from falling off the scaffolding.
BefoRe eRecting access fRame scaffolding
n What will the scaffolding be used for? For example, light duty (one or two workers;
painting a wall), or heavy duty (several tradespersons, with large and heavy materials
on the platform)?
n How high will the scaffolding be? Will it be erected in one operation or as
the work progresses?
n Is the ground rm? Can it support the loads from the scaffolding, workers, and
materials on it?
n Will the scaffolding need to be tied in? How will this be done? Will the ties be moved
as the work progresses?
n Is the scaffolding likely to be covered or enclosed as a protection against the elements?
Is there provision for adding additional ties to the adjoining structure?
n What will be the method of access and egress? For example, a sloping ladder, vertical
ladder, built-in stairway, or direct from the oors of the building structure?
n On a multi-level scaffolding, how many levels will be loaded with materials at one time?
Will an engineer be required to make the calculations for the total anticipated loading
and possibly design the scaffolding and the sills?
n If a rolling scaffolding is required, consider ground surface, height restriction (3 to 1 rule)
hazards when moving (such as power lines, projections from the building, and potholes).
equipment inspection
YOU MUST INSPECT THE EQUIPMENT YOU PLAN TO USE TO MAKE SURE THAT IT IS IN GOOD
REPAIR AND SUITABLE FOR THE JOB. CHECK THE FOLLOWING:
n Sills: suitable size and strength for the loads. Not split or rotten.
n Frames: no cracks in the welded joints. No kinks or dents in the top or bottom
cross-members. Legs plumb and square with the cross-members. Brace locks in good
working order. Coupling pins in place and secured to the frame.
n Cross braces and diagonal braces: straight with no bent ends. Pivot connection in good
working order. No excessive rust.
n LEELITE™ Planks: no split ends, saw cuts, notches, protruding nails, excessive warping.
No contamination that may affect the integrity of the plank, such as oil, chemicals, and
burns. (If you have any doubts about the strength of the plank, you may need to
have it load-tested).
n All aluminium or with plywood deck platforms: not mis-shaped or cracked. Locks working.
All bolts and screws in place. No burns or broken ends. If upper surface has non-skid
coating, no rot or plywood separation on underside.
n Side or end brackets: hook-on attachment not distorted. No cracks in welds. No dents,
kinks, or any signs of abuse.
n Guardrails: straight, with no kinks, dents, or excessive rust.
n Casters: same size and from same manufacturer. Wheel rotates well and the swivel
below the stem is working. Brake mechanism works properly. Wheel tread has no damage.
n Screw jacks: no cracks in weld where screw jack is attached to the top of the caster.
No thread damage. No curling or warping of the base plate. Adjusting nut is a tight t.
n Other equipment: inspect any other equipment in the frame structure. Damaged
equipment should be tagged and marked as not t for use. Inform the supervisor so
that others do not use it.
1
WORKSAFEPAD02BI10

Summary of content (1 pages)