Operation Manual
MI 3309 BT DeltaGT Single test
43
Figure 5.26: Examples of polarity test result
Displayed results:
Main result ............. PASS/FAIL, description of fault
Note:
Consider any displayed warnings before starting test!
5.2.8 Differential leakage
The purpose of this test is to determine the sum of all leakages flowing from the live
conductors to the earth. The differential method allows measuring the full and true leakage
current, even if there are parallel current paths from the DUT to ground.
The instrument measures:
The differential leakage of the DUT connected to the instrument test socket.
Figure 5.27: Differential leakage current menu
Test parameters for differential leakage current measurement
OUTPUT Test voltage [MAINS voltage]
LIMIT
Maximum current [0.25 mA, 0.50 mA, 0.75 mA, 1.00 mA, 1.50 mA,
2.00 mA, 2.25 mA, 2.50 mA, 3.50 mA, 4.00 mA, 4.50 mA, 5.00 mA,
5.50 mA, 6.00 mA, 7.00 mA, 8.00 mA, 9.00 mA, 10.0 mA, 15.0 mA, --- mA]
TIME Measuring time [2s, 3s, 5 s, 10 s, 30 s, 60 s, 120 s, --- s (continuous
measurement)]