3.3.1 Task State
The task can be switched on or off in the task status window as illustrated below. Tasks that are switched off will be ignored by the system.
Tasks which are switched on may be modified or updated.
Note: The date when the Test Sequence is scheduled to take place will be recalculated as soon as the Task State is saved by
pressing OK”. The due date of the next subsequent occurrence is calculated at the end of each executed Test Sequence.
A complete list of the settings can be printed out by pressing the «F» key while the Task State menu is open.
3.3.2 Assigning a Test Sequence to the Task
An existing Test Sequence can be assigned to the Task. On selecting Test Sequence”, the user can select from a list of previously
configured Test Sequences.
Tasks Setup
Sensitivity Manual
Task 02 Off
Task 03 Off
Task 04 Off
Task 05 Off
Task 06 Off
Task 07 Off
Task 08 Off
Task 09 Off
Task 10 Off
Task 11 Off
Task 12 Off
OK
Task State
Task
Setup
Off
On Manual
OK
Task # Setup
Test Sequence Define
Starting Method Manual
Defined Days Define
Defined Users Define
OK
Selection that appears are the
names of the test sequences
that you have previously de-
fined in the Test Routine List
(see section 3.2.1)
C
Task State
Task
Setup
Off
On Manual
OK