5.4 PROCEDURE TO INSTALL THE AIR CHANNELS AND DRAFT TOWERS
(ONLY “DD” MODELS)
MODELS: MDD23-E, MDD58-E, MDD68-E, MDD78-E & MDD94-E
This procedure describes how to install the air channel needed to provide cold air
directly into the beer towers.
TOOLS NEEDED: Philips screwdriver
STEP 1 Locate the gaskets and bolts included in with your Tower. Place gasket
over the pre-drilled holes and place the 4 screws thru the tower base.
Align the tower with screws and gasket to the cabinet top as shown
below while dropping the beer line(s) thru the top of the unit (Figure #1).
STEP 2 Tighten the screws using the nuts found in your tower box (Figure #2).
STEP 3 Identify the “COLD AIR HOSE” (Figure #3) which is found inside of
the equipment.
STEP 4 Introduce the “COLD AIR HOSE” (Figure #4) which is found inside of
the equipment into the tower’s base hole.
Push the cold air hose as far as possible up into the tower body. Be sure
and secure cold air hose by hooking on to beer hose elbow.