Installation Guide

Wi-Fi WASP Infrastructure Installation Guide
Installation Guide
Section 4 Installing Infrastructure
Rev: 1 20 / 28
© Minetec 2019
If site-specific Work Instructions exist for any of the tasks described in this section, use those Work
Instructions instead of these guidelines.
Guide 3 Installing an ICT Cabinet
For best performance and hardware integrity, follow these guidelines when installing an ICT Cabinet.
Step
Action/Response
Comments
1) Install the
mounting
option.
Confirm the mounting option.
If using a threaded rod, drill and
install the rod to the verified
position and allow Chemset (or
equivalent) to set.
If using a different mounting option,
install any required mounts to the
cabinet.
Mesh mounting is only recommended for
temporary installations.
Use the approved detailed design
documents and drawings for
reference when commencing
installation.
2) Attach the ICT
cabinet.
Attach the cabinet to the mounting
point.
If using a hanging frame, attach
with chain from an eye bolt.
If using threaded rod, attach to
the threaded rod using the
appropriate nuts and washers.
3) Check power
is off
Ensure the power cables to be
connected are not live.
Power supply to the cabinet should
be positively isolated and tagged.
4) Install and
connect the
cables.
Install power cable from the Access
Points and connect to the cabinet
Gateway power port.
Connect Bridge power cable and run
to the power injection point.
Run the Ethernet cable and connect
to the ICT Cabinet Ethernet port.
Secure all cables with cable ties.
5) Check
connections.
Check all connections, cables and anchor
points are secure.
Perform this before connecting to
power.
6) Perform
power-on
check.
When all devices connected, perform a
power-on check.
Refer to Section 4.3.3 on page 21
.
7) Mark up.
Mark up (red line) installation drawings
to indicate any changes to installation
locations (cabling or Bridge).
Installation of the device is now
complete.