Allowable loads and deection values for holdowns such as TD, PHD,
TDX, HTT and UPHD are based on installation with the anchor bolt
aligned directly below the centerline of the holdown. The maximum
tolerances for anchor bolt offset are described below.
Designer should consider that installation of a holdown raised above the
sill plate may result in higher deections. These deections are different
for every installation and should be calculated by a certied designer.
Installation:
Holdown installed at maximum of 2' above the bottom plate.
Anchor bolt installed at maximum 2" away from the centerline
of the holdown.
Threaded rod angle must not exceed 5 degrees or a pitch of 1/12.
A threaded coupler must be used at the anchor bolt connection
capable of developing 125% of strength of the rod.
Alternate installations:
1. Install additional full-height member(s) to the existing stud(s)
or post to reduce the horizontal distance between the anchor
bolt and the vertical member(s).
Multi-ply studs/posts must be fastened together to act as
a single unit. Holdown fasteners must not be considered
to contribute to fastening multiple members together.
• Added members shall be of equal or better wood species.
Designer must consider any effect of additional eccentricity
introduced on the connection.
2. Using a threaded rod epoxied into place at the proper location in
lieu of cast-in anchor bolts. These can be installed after the rough
framing is completed.
Holdown Offset Anchor Bolt Notes
Full height stud
or post per plan
MiTek holdown
per plan
Threaded rod to
match anchor bolt,
double-nut at holdown
Threaded coupler
capable of developing
125% of strength
of the rod
Foundation
Anchoring device
2"
Max
2'
Max
1
12