5. Drainage piping work
4. Installing the refrigerant piping
Outdoor unit drainage pipe connection
When drain piping is necessary, use the drain socket or the drain pan (option).
However, it can not be used for MXZ-SM36/42/48NAMHZ (Hyper Heating model)
Drain socket PAC-SG61DS-E
Drain pan PAC-SH97DP-E
Fig. 4-12
4.6. Stop valve opening method
The stop valve opening method varies according to the outdoor unit model. Use the
appropriate method to open the stop valves.
(1) Gas side (Fig. 4-10)
1 Remove the cap, pull the handle toward you and rotate 1/4 turn in a counterclock-
wise direction to open.
2 Make sure that the stop valve is open completely, push in the handle and rotate
the cap back to its original position.
(2) Liquid side (Fig. 4-11)
1 Remove the cap and turn the valve rod counterclockwise as far as it will go with
the use of a 4 mm [3/16"] hexagonal wrench. Stop turning when it hits the stopper.
2 Make sure that the stop valve is open completely and rotate the cap back to its
original position.
Precautions when using the charge valve (Fig. 4-12)
Do not tighten the service port too much when installing it, otherwise, the valve core
could be deformed and become loose, causing a gas leak.
After positioning section B in the desired direction, turn section A only and tighten it.
Do not further tighten sections A and B together after tightening section A.
Warning:
When opening or closing the valve below freezing temperatures, refriger-
ant may spurt out from the gap between the valve stem and the valve body,
resulting in injuries.
When installing the unit, securely connect the refrigerant pipes before
starting the compressor.
* Theguretotheleftisanexample
only.
The stop valve shape, service port
position, etc., may vary according to
the model.
* Turn section A only.
(Do not further tighten sections A and
B together.)
C Charge hose
D Service port
<Example>
Outdoor model : MXZ-SM48NAM A : ø9.52 30 m (98 ft)
<Additional Charge>
Calculation of refrigerant charge
Pipe size
Liquid pipe
ø6.35
+
Pipe size
Liquid pipe
ø9.52
+
Total capacity
of connected
indoor units
Amount for the
indoor units
SM36/42/48
(m) × 19.0 (g/m)
((ft) × 0.21 (oz/ft))
SM36/42/48
(m) × 50.0 (g/m)
((ft) × 0.55 (oz/ft))
– 27
1.5 kg (53 oz)
28 – 54
2.5 kg (88 oz)
SM60
(m) × 27.0 (g/m)
((ft) × 0.29 (oz/ft))
SM60
(m) × 70.0 (g/m)
((ft) × 0.75 (oz/ft))
55 –
3.0 kg (106 oz)
Included refrigerant amount when shipped from the factory
Included refrigerant amount
SM36/42/48
4.8 kg (169 oz)
SM60
5.1 kg (180 oz)
4.7. Additional refrigerant charge
Additional refrigerant charge
Refrigerant for the extended piping is not included in the outdoor unit when the unit is
shipped from the factory. Therefore, charge each refrigerant piping system with addi-
tional refrigerant at the installation site. In addition, in order to carry out service, enter
the size and length of each liquid pipe and additional refrigerant charge amounts in
the spaces provided on the “Refrigerant amount” plate on the outdoor unit.
* When the unit is stopped, charge the unit with the additional refrigerant through
the liquid stop valve after the pipe extensions and indoor units have been vacu-
umized.
When the unit is operating, add refrigerant to the gas check valve using a safety
charger. Do not add liquid refrigerant directly to the check valve.
Calculation of additional refrigerant charge
Calculate the additional charge using the liquid pipe size and length of the ex-
tended piping and total capacity of connected indoor units.
Calculate the additional refrigerant charge using the procedure shown to the
right, and charge with the additional refrigerant.
For amounts less than 0.1 kg, round up the calculated additional refrigerant
charge.
(For example, if the calculated charge is 6.01 kg, round up the charge to 6.1 kg.)
The total length of each liquid line is as follows:
ø9.52 : A + a = 30 + 15 = 45 m (148 ft)
ø6.35 : b + c + d = 10 + 10 + 20 = 40 m (131 ft)
The total capacity of connected indoor unit is as follows:
24 + 15 + 08 + 08 = 55
<Calculationexample>
Additional refrigerant charge
40 ×
19.0
+ 45 ×
50.0
+ 3.0 = 6.1 kg (rounded up)
1000 1000
(131 × 0.21 + 148 × 0.55 + 106 = 215 oz)
Indoor 1 : model 24 a : ø9.52 15 m (49 ft)
2 : model 15 b : ø6.35 10 m (33 ft)
3 : model 08 c : ø6.35 10 m (33 ft)
4 : model 08 d : ø6.35 20 m (66 ft)
At the conditions