Installation and Service Manual
Table Of Contents
12
6-584.13
INSTALLATION - GAS CONNECTIONS
GAS CONNECTIONS
1.  Installation of piping must conform with local building codes, 
or in the absence of local codes, with the National Fuel Gas 
Code, ANSI Z223.1 (NFPA 54) - latest Edition. In Canada, 
installation must be in accordance with CSA-B149.1.
2.  Piping to units should conform with local and national 
requirements for type and volume of gas handled, and 
pressure drop allowed in the line. Refer to Table 12.1 to 
determine the cubic feet per hour (CFH) for the type of gas 
and size of unit to be installed. Using this CFH value and the 
length of pipe necessary, determine the pipe diameter from 
Table 12.2. Where several units are served by the same 
main, the total capacity, CFH and length of main must be 
considered. Avoid pipe sizes smaller than 1/2". Table 12.2 
allows for a 0.3" W.C. pressure drop in the supply pressure 
from the building main to the unit. The inlet pressure to the 
unit must be 6-7" W.C. for natural gas and 11-14" W.C. for 
propane gas. When sizing the inlet gas pipe diameter, make 
sure that the unit supply pressure can be met after the 
0.3" W.C. has been subtracted. If the 0.3" W.C. pressure drop 
is too high, refer to the Gas Engineer’s Handbook for other 
gas pipe capacities.
3.  Install a ground joint union with brass seat and a manual 
shut-off valve adjacent to the unit for emergency shut-off 
and easy servicing of controls, including a 1/8" NPT plugged 
tapping accessible for test gauge connection (see Figure 12.1). 
4. Use 2 wrenches when connecting field piping to units. 
5.  Provide a sediment trap before each unit in the line where 
low spots cannot be avoided (see Figure 12.1).
6.  When pressure/leak testing, pressures above 14" W.C. 
(1/2 psi), close the field installed shut-off valve, disconnect 
the appliance and its combination gas control from the gas 
supply line, and plug the supply line before testing. When 
testing pressures 14" W.C. (1/2 psi) or below, close the 
manual shut-off valve on the appliance before testing.
Figure 12.1 - Recommended Sediment Trap/Manual 
Shut-off Valve Installation - Side or Bottom Gas 
Connection 
j
j
 Manual shut-off valve is in the “OFF” position when handle is perpendicular to pipe.
IMPORTANT
To prevent premature heat exchanger failure, the input to the 
appliance, as indicated on the serial plate, must not exceed 
the rated input by more than 5%.
Table 12.1 - Sea Level Manifold Pressure & 
Gas Consumption
      Natural Propane
Model  BTU/Cu. Ft.  1050  2500  No. of
Size  Specific Gravity  0.60  1.53  Orifices
Manifold Pressure In. W.C.  3.5  10.0
  CFH  28.6  12.0  2
    Gal/Hr. Propane    .33
    Sec/cu. ft.  126  300 
    Orifice Drill Size  49  56
  CFH  42.9  18.0  3
    Gal/Hr. Propane    .50
    Sec/cu. ft.  84  200 
    Orifice Drill Size  49  56
  CFH  57.1  24.0  4
    Gal/Hr. Propane    .66
    Sec/cu. ft.  63  150 
    Orifice Drill Size  49  56
  CFH  71.4  30.0  5
    Gal/Hr. Propane    .83
    Sec/cu. ft.  50  180 
    Orifice Drill Size  49  56
    CFH  95.2  40  5
  Gal/Hr.Propane    1.09 
    Sec/cu. ft.  38  90 
    Orifice Drill Size  45  55 
    CFH  119  50  5
  Gal/Hr.Propane    1.37 
    Sec/cu. ft.  30  72 
    Orifice Drill Size  42  53 
30
45
60
75
100
125
Pipe 
Length (ft)
Natural Gas
1/2" 3/4" 1" 1-1/4" 1-1/2" 2"
10 132 278 520 1050 1600 3050
20 92 190 350 730 1100 2100
30 73 152 285 590 890 1650
40 63 130 245 500 760 1450
50 56 115 215 440 670 1270
60 50 105 195 400 610 1150
70 46 96 180 370 560 1050
80 43 90 170 350 530 930
100 38 79 150 305 460 870
125 34 72 130 275 410 780
150 31 64 120 250 380 710
Table 12.2 - Gas Pipe Capacities - Natural Gas 
jk
j
  Capacities in cubic feet per hour through Schedule 40 pipe with maximum 
0.3" W.C. pressure drop with up to 14" W.C. gas pressure. Specific gravity is 
0.60 for natural gas and 1.50 for propane gas.
k
  For pipe capacity with propane gas, divide natural gas capacity by 1.6. Example: 
What is the propane gas pipe capacity for 60' of 1-1/4" pipe? The natural gas 
capacity is 400 CFH. Divide by 1.6 to get 250 CFH for propane gas. 
  WARNING
1.   All field gas piping must be pressure/leak tested prior to 
operation. Never use an open flame. Use a soap solution or 
equilavent for testing.
2. Gas pressure to appliance controls must never exceed 
14" W.C. (1/2 psi).
3. To reduce the opportunity for condensation, the minimum 
sea level input to the appliance, as indicated on the serial 
plate, must not be less than 5% below the rated input, or 
5% below the minimum rated input of dual rated units.
 CAUTION
1. Purging of air from gas lines should be performed as   
described in ANSI Z223.1 - latest edition “National Fuel   
Gas Code”, or in Canada CSA-B149 codes.
2. When leak testing the gas supply piping system, the   
appliance and its combination gas control must be isolated  
during any pressure testing in excess of 14" W.C. (1/2 psi).
3. The unit should be isolated from the gas supply piping   
system by closing its field installed manual shut-off   
valve. This manual shut-off valve should be located within   
6' of the heater.
4. Turn off all gas before installing appliance.










