Specifications
Operating the Machine
TX,35,DH2276 –19–02OCT92–3/3
T7208AV –UN–30JAN90
Normally, a bank or stockpile is excavated from the
bottom and then up the side. Work the face of the bank
or stockpile evenly to prevent outcroppings and
overhangs.
Work bank or stockpile with machine at a 90° angle to the
bank or stockpile.
1. Position bucket on the ground in return-to-dig position.
2. Move transmission control lever to 1st or 2nd gear
depending on ground conditions.
In loose material, use 2nd gear for better traction. Use
1st gear for better bucket fill.
3. Move forward into the bank or stockpile.
NOTE: Use differential lock as necessary.
4. Raise and curl bucket as bucket fills.
TX,35,JC1049 –19–17JAN96–1/4
USING THE LOADER BUCKET
T7747BB –UN–19MAY92
1. Place bucket in the return-to-dig position and lower to
ground.
NOTE: Bucket and boom can be positioned while
machine is on-the-go.
2. Move transmission control lever to 1st or 2nd gear
depending on ground condition.
3. Move forward into the material.
35–10
PN=81