Specifications
Operating the Machine
TX,35,DH2278 –19–31JUL92–1/1
BACKDRAGGING
T7747BG –UN–19MAY92
Leveling and grading can be done with the boom in the
float position by backdragging the loader bucket while
traveling in reverse. (Float position allows the bucket to
follow contour of the ground.)
TX,35,JC1064 –19–14FEB96–1/1
BACKFILLING
T6603AO –UN–20OCT88
There are two effective methods of backfilling.
IMPORTANT: DO NOT bulldoze with bucket in the
dump position, as damage could result
to the bellcrank linkage. When dozing,
keep bucket bottom parallel to the
ground.
1. Use loader bucket as a dozer. As bucket approaches
the trench, material being pushed will fall into the
trench. Reverse direction and reposition loader to
maintain a 90° angle to the trench line.
2. Push material to the trench as in method 1. Use clutch
cut-off to maintain high engine rpm.
Dump material into the trench while placing direction
selector lever in neutral.
When bucket is dumped, release clutch cut-off and
reposition loader for a 90° angle to the trench line.
If filling, spread material in thin layers. Operate at
nearly full rpm and dump material on-the-go. Reverse
direction just prior to emptying bucket. Loader will
compact fill material as it works.
35–12
PN=83