Section 3-2: INSTALLING A ROOF MOUNTED DIRECT VENT
TERMINATION (MVTK-1 / PVTK-1)
This section applies to installations where the direct vent termi-
nation will be roof mounted.
Section 3-2-1: VENTING LAYOUT
Selection of components and details of venting lay out should
adhere to the following guidelines:
The maximum termination point is 32’ above the replace (NOTE:
if the maximum termination height is used, the ame pattern
may be affected).
The Vertical termination must be a minimum 2’ higher than where
the termination exits the roong materials, (asphault shingles,
cedar shakes, etc). This distance should be measured from the
high side of the roof slope where the ue ashing intersects the
roong materials. (see Figures 11 to 11c *).
Termination location must be a minimum 6’ from a mechanical
air inlet.
Termination location must be a minimum 18” from a parapet wall.
A maximum of two offsets (each offset is made up of 2-90°
bends) may be made.
Install a restop at any location where venting passes through
combustible materials and construction.
Utilize support straps, or support plates, and rings (as required)
to meet acceptable building practices.
Install all roof ashing and storm collars as shown.
Figure 11. Top vent, Roof mounted termination with no offset in
vent run.
Figure 11a. Top vent, Roof mounted with 1 offset (1 offset= two 90°
bends).
Figure 11b. Top vent, Roof mounted with 2 offsets (1 offset= two 90°
bends).
Roof mounted Terminations
The following details are some possible congurations for Roof
mounted terminations. See below.
Support ring
Support plate
Firestop
32’ max.
2’ min.
PVTK1
Termination
Support ring
Support plate
Firestop
32’ max.
2’ min.
Obstacle
PVTK1
Termination
Support straps or
support plate & ring
2’ min.
Firestop
Firestop
2’
Firestop
32’ max
Support plate
& ring
Obstacle
PVTK1
Termination
MVTK-1 / PVTK-1
Termination
MVTK-1 / PVTK-1
Termination
MVTK-1 / PVTK-1
Termination