Owner`s manual
Page 15
C-View Residential R520-R620 Series Indoor Gas Fireplace
Part No. XG0771 - 070111
f i r e f e a t u r e
combustibles), Figure 16b. Next, cut four vertical 2 x 4's to install between the Upper and Lower Horizontal 2 x 4's, (2-pcs either side). (En-
sure these are placed the required 1" clearance to combustibles). Cut the top 2 x 4 (horizontal) to t between the vertical 2 x 4's (iether side of
replace) as shown. Last, install the Supplied Steel Header 1" above the replace throat.
Figure 16b. Fireplace installation, (Ensure you maintain the 1" clearance to combustibles).
Step 4. As shown in Figure 16c; Cut a sheet of Non-combustible concrete board to overlap the new Horizontal & Vertical 2 x 4's, See Figure
16b, Above. Place the Non-combustible wall board above the replace throat, allowing 1/8" clearance from the rim above the replace opening.
Pre-drill the board with 1/8" drill and secure to framing with Nails, use at heat sheet metal screws to fasten the board to the metal header.
Figure 16c. Non-combustible Board over the Fireplace, (supplied by Montigo).
Non-Combustible header,
(supplied by Montigo)
1” clearance
1” clearance
1” clear-
ance
1” clear-
ance
2-pcs 2 x 4 (vertical)
Both Sides Typ.
2 x 4
(horizontal)
2 x 4
(horizontal)
Non-Combustible cement board,
(supplied by Montigo) or Equiv.
Pre-drill for Nail fasteners
Combustible framing
Sheet metal Screws to attach Non-Combustible
cement board to Steel header.
1/8”
Clearance required for
expansion of the fireplace
when in operation.
Installation