44 User Manual RKP-II (CA53461-001; Version 2, January 2010) © 2010 Moog GmbH
7.1.1 Filling up the Pump
Filling up the Pump
Procedure:
1. Fill the pump through the leakage oil port with operating fluid 
completely.
Multiple pump circuits
7.1.2 Adjusting the Compensator
Adjusting the 
Compensator
The following information is the same for F, H, J and R compensators:
Tightening torque for the lock nuts of the adjusting screw for adjusting the 
compensator pressure: SW 19 = 10 Nm + 5 Nm
Procedure:
1. Depending on the compensator, refer to the respective subchapter.
2. If required: Adjust the compensator according to the information provided 
in the subchapter.
3. For G compensators: Adjust the compensator using the lockable 
adjustment knob.
WARNING Risk of injury and property damage as a result of fire!
Easily inflammable operating fluid may cause fire.
• Keep the pump away from any open flames.
WARNING Risk of Burns!
Pump parts run hot while in operation.
• Do not touch the pump while it is running.
WARNING Risk of injury and property damage as a result of 
engaging or winding!
Freely accessible rotating machine / equipment parts may lead 
to severe injuries or property damage as a result of engaging 
or winding.
• Use suitable protective devices to ensure that access to 
the drive shaft is blocked.
The pump must be completely filled with operating fluid before initial 
operation.
For vertical installation: Before operation the pump housing of all pump 
stages must be filled completely with hydraulic fluid via the leakage 
connection.
Information on the compensator functions: 
Ö Chap. "3.5 Compensator Operation", Page 15
All compensators are pre-set at the factory. In this section, information on 
the parameters needed to adjust the compensators is provided.