User's Manual

Table Of Contents
3. Installation 3
ODU 1 ODU 2
SDIDU 1 SDIDU 2
30dB 30dB20dB
10W 2W 10W
Ant.
Port
Ant.
Port
TNC IF
Cable
(supplied)
TNC IF
Cable
(supplied)
Figure 3-2. Event-HD Back-to-Back Testing Configuration
3.5Overview of Installation and Testing Process
The installation and testing process is accomplished by performing a series of separate,
yet interrelated, procedures, each of which is required for the successful implementation
of a production Event-HD network. These procedures are as follows:
Site Evaluation: gathering specific information about potential Event-HD radio™
installation sites.
Cable and Installation: Testing and installing ODU cables and optional interface
devices at installation sites.
Event-HD ODU Mounting and Alignment: Mounting ODUs to a pole or wall, performing
link alignment and radio frequency (RF) verification.
Event-HD Digital Radio Configuration: Using Event-HD Link Manager software to
install network- and site-specific parameters in the radios.
Event-HD Digital Radio Testing: Performing cable continuity checks and RF tests for
links, the payload/radio overhead channel, and the management channel.
The following diagram shows where installation and commissioning resides within the
Event-HD network deployment life cycle and defines the sequence in which the processes
that comprise installation and commissioning should be performed.