Instruction Manual

Table Of Contents
Chapter 3
GTR 8000 Base Radio Installation
This chapter details installation procedures relating to GTR 8000 Base Radio.
3.1
Pre-Installation Tasks
Follow this process to perform the installation tasks. Ensure that you have the following:
Appropriate cables
Access to Software Download Manager (SWDL), Configuration/Service Software (CSS), and the
Unified Network Configurator (UNC)
IP/DNS information
Login and password information
3.1.1
Equipment Installation Process Overview
Process:
1 Prepare the site to comply with the Motorola Solutions requirements and specifications for the
equipment, as listed in the Standards and Guidelines for Communication Sites manual. The
base radio may be installed in a suitable, restricted access, indoor enclosure in any location
suitable for electronic communications equipment. Other codes and guidelines that may apply to
the location must also be met. See General Safety Precautions on page 83.
2 Inspect and inventory all racks, cabinets, cables, and other equipment with a Motorola Solutions
representative to ensure that the order is complete. See General Installation Standards and
Guidelines on page 86.
3 Various tools are used to install and service the equipment. If information is needed regarding
where to obtain any of the equipment and tools listed, contact the Motorola Solution Support
Center (SSC). See General Installation/Troubleshooting Tools on page 92 for a list of general
recommended tools for installing and servicing the hardware.
4 Install all equipment using the site drawings and other documents provided by the Field
Engineer. Use the installation standards and guidelines for placing and installing equipment.
5 Properly ground all the racks and cabinets to protect against ground faults, electrical surges, and
lightning. See GTR 8000 Base Radio Hardware Installation on page 94.
6 Connect all necessary cables within a rack and between the racks for system interconnection.
See GTR 8000 Base Radio Rear Connections (Integrated Voice and Data) on page 106, GTR
8000 Base Radio Rear Connections (HPD) on page 109, and GTR 8000 Base Radio Front
Connections on page 111.
7 Run a preliminary check of a site before applying power.
8 See Installing Device Software Prerequisites on page 122 for a list of items you need access to
before installing the software.
9 See Installing Devices in the UNC on page 126 to discover the base radio and to load OS
software images from the UNC.
MN003286A01-H
Chapter
3: GTR 8000 Base Radio Installation
82