Installation Guide

Premium Luxury Vinyl Flooring Installation Instructions for MSI 2MM and 2.5MM Glue-Down Products
General Information
It is important that MSI flexible glue-down flooring products maintain proper temperature before, during, and after
installation in order to minimize dimensional changes. The subfloor, all flooring material, and the adhesive must be
conditioned at a constant temperature between 65˚F (18˚C) and 85˚F (29˚C) for 48 hours prior to, during, and 48 hours
after installation. Thereafter, maintain a room temperature between 55˚F (13˚C) and 95˚F (35˚C). When using flooring
from two or more cartons, make sure pattern and run numbers found on the carton are the same. This information is
on the outside end of each carton.
Tools and materials
Universal pressure sensitive LVT adhesive or Multi-use LVT adhesive
Trowel (1/16” x 1/32” x 1/32” for adhesive)
100 pound, 3 section roller
Chalk Line
Carpenter square
Utility Knife
Cutting board
Tape measure
In Situ probes, Moisture Meter, and/or Calcium Chloride Test Kit
Preparing the Area
Remove all furniture, appliances, and fixtures from the room.
Remove all binding strips or other restrictive molding from doorways, walls, etc.
Undercut wood door casings where possible so that flooring can be slid under it
Subfloor Preparation
Asbestos Warning
WARNING! DO NOT MECHANICALLY CHIP OR PULVERIZE EXISTING RESILIENT FLOORING, BACKING, LINING FELT,
ASPHALTIC “CUTBACK” ADHESIVES OR OTHER ADHESIVES. Installed resilient floor covering products and the asphaltic
or cutback adhesives used to adhere them may contain either asbestos fibers and/or crystalline silica. The products in
this carton DO NOT contain asbestos or crystalline silica. Avoid creating dust or inhalation of asbestos/crystalline dust
as they can cause cancer and respiratory tract hazard. Smoking by individuals exposed to asbestos fibers greatly
increases the risk of serious bodily harm. Unless positively certain that the previously installed product is a non‐asbestos
containing material, you must presume it contains asbestos. Regulations may require that the material be tested to
determine asbestos content and may govern the removal and disposal of material. See current edition of the Resilient