117: Install the Mounng Rail into the beam clamps
slot as per Mounng Rail instrucons. Use 3/8” x 1”
stainless steel bolts and 3/8” serrated ange nuts.
118: Center rails over I-beams, keeping equal length of
rail o the end of each beam. Tighten to 17 lbs.
Install Solar Modules as per Mounng Rail and module
manufacturer instrucons. See last page of manual for
Iron Ridge Rail and Clamp instrucons.
204” Rail Connecon
117
119
120
119: Leave out the appropriate module(s) to allow for the 8” pipe. It is ok to install the top and boom
modules of the center row(s) with just 2 clamps unl the array is lied to the top. Raise and or lt the
array to facilitate module installaon and/or module wiring and wire management as needed.
120: When wiring is completed, raise the array to the top of the pole.