iPasolink250 Installation and Commissioning Guide Document ID: 141-DOC000008-E
SI.No
Site Verification
Checkpoints
Status
(Yes/No)
Measurements (Mts)
Remarks
If no, has a suggestion /
recommendation been
communicated?
This should be recorded
in the Remarks Column
5
Is there adequate
distance between DCDB
and rack for extension
of Power cables
If no, has a suggestion
or recommendation
been communicated?
This has to be recorded
in the Remarks Column
<< Record the
measurement here >>
6
Is there adequate
distance between
Ground point and the
rack?
If no, has a suggestion
or recommendation
been communicated?
Has this been recorded
in the Remarks Column?
<< Record the
measurement here >>
7
Is Rectifier available at
Site and is powered on?
8
Has Type of DS1/DS3
DDF available and
verified (Poyet, Krone,
Wrapping, RJ45)?
9
Is there an FDF
available at the site?
10
Is there adequate
distance between the
FDF and the equipment
for fiber patch chords?
<< Record the
measurement here >>