Cabinet Requirements
2-2 Express5800/320Fc: Site Planning Guide
To prevent stray voltages, all components are grounded together through the
vertical mounting rails to the cabinet frame, and then to local building ground. To
ensure signal quality, use a grounding cable provided by NEC Corporation of America
for local building ground.
There is a plan for maintaining cables and wires to the cabinet by either running
them under the floor or placing them overhead in an overhead cable tray.
Air flows through the cabinet from front to back.
Filler panels cover any unused rack space to prevent air recirculation.
Vents are evenly distributed on the front and rear doors and comprise at least 63%
of the surface area.
NOTE
If your cabinet does not have vented front and rear doors,
you can remove the doors from the cabinet while your
Express5800/320
Fc system is
operating.
Figure 2-1 shows the required rail clearance between the front vertical rails and the
inside edge of an accessory leg.