Installing the Inside Version
14 R900i SP Inside and Pit Installation and Maintenance Guide
Checklist
Before leaving the installation site, be sure to:
Table 5 Checklist Before Leaving Site
Record MIU ID for each register.
Verify that you have followed all requirements of this
Quick Install Guide.
Verify that you have recorded all required information.
Clean up any installation debris.
Verify that the requirements of the site work order
have been completed.
R900i SP Inside and Pit Installation and Maintenance Guide 15
6 Installing the Pit Version
This section describes storage and unpacking instructions, preliminary tests, tools,
materials, site selection, and pit installation of theR900i SP version MIU.
Prior to Installation
Storage
Upon receipt, inspect shipping containers for damage and inspect the contents of
any damaged cartons prior to storage.
The unit should be in sleep mode until it is exposed to light. The unit should not be
transmitting until the box is opened and the unit is exposed to a light source.
Unpacking
As with all precision electronic instruments, the R900i SP MIU should be
handled carefully; however, no additional special handling is required.
After unpacking the MIU, inspect it for damage. If the MIU appears to be damaged
or proves to be defective upon installation, notify your Neptune Sales Representative.
If one or more items requires reshipment, use the original cardboard box and
packing material.
Figure 6 R900i SP Pit Installation
Installing the Pit Version
16 R900i SP Inside and Pit Installation and Maintenance Guide
Tools Needed
Table 1 on page -5 shows the recommended tools you need to successfully install
the R900i SP or replace the MIU’s internal battery.
Site Selection
Installation and operation in moderate temperatures increase reliability and product
life. See “Environmental Conditions” on page 3.
Follow these guidelines when selecting a location to install the R900i SP:
• The R900i SP must be installed in a vertical and upright position.
• The selected location should be clear of all obstructions.
• Some items may not apply to your specific installation or the list may not contain
all required tools or materials.
Installing the R900i SP Pit Version MIU
The following are steps for installation of the R900i SP pit