Operating Guide

10
If there are pre-installed baseboards in need of replacement, remove old baseboards and
quarter rounds.
If new baseboards and quarter rounds need to be installed, install these items after the oors
have been completed.
Chisel any uneven surfaces on the oor and wall before starting the install.
Ensure the general space preparation has been completed before starting install. Reference
page 8.
Ensure Concrete suboor, Radiant heating or wood suboor requirements has been followed.
Reference page 8-9.
NewAge Stone Composite ooring can not be installed with pre-installed quarter rounds. All
Quarter rounds need to be removed before starting install.
Once all quarter rounds have been removed, cut approximately 11mm o the bottom of your
baseboards to have enough space for the 9.5mm oor planks or tiles.
Note: If previous oors are thicker than the new Luxury Vinyl Floors, you may need to
purchase a new door casing or plinth block.
Quarter rounds will need to be installed after the ooring is complete.
Ensure the general space preparation has been completed before starting install. Reference
page 8.
Ensure Concrete suboor, Radiant heating or Wood Suboor requirements has been followed.
Reference page 8-9.
Option 1: Installing Interior ooring before baseboards and quarter rounds.
Option 2: Installing Interior ooring with pre-installed baseboards and
quarter rounds.
Baseboard and Quarter Round Preparation